Unable to edit or add columns, edit project setting is greyed out

Options
Mouly
Mouly
edited 03/15/23 in Formulas and Functions

Hi,


I am unable to edit the columns nor edit project settings. I am co-owner of a project plan and wanted to add a few more columns.

Have the license and not sure why it prevents me from editing.

If I am the owner of a new sheet, I am able to


thank you

Mouly

Answers

  • Genevieve P.
    Genevieve P. Employee Admin
    Options

    Hi @Mouly

    Even if you have a license, you'll still need to be shared to the sheet with at least Admin or Owner permissions in order to add columns or adjust project settings.

    Can you check the Share window to see what level of permissions you have on this item? You may need to reach out to the current owner and ask for an upgrade. (See: Sharing permission levels and tasks)

    Cheers,

    Genevieve