Report: Show me child tasks ONLY if the parent is In-Progress
Allen4480
✭✭
Hello,
I'd like to build a report.
My goal is to see only "Milestone" tasks (of any status), but only when the Parent Status is "in-progress".
I can't seem to find the right combination of filters to build this report? Can you help?
thank you tons!
Tags:
Best Answer
-
You would need a helper column that brings the parent status onto each row. You would then filter the report by this helper column and the activity type column.
Answers
-
You would need a helper column that brings the parent status onto each row. You would then filter the report by this helper column and the activity type column.
-
Paul, you're a genius! Tell your boss to give you a raise!
worked like a charm!...
big thank you!!!
-
Happy to help. 👍️
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!