Hello,
I'd like to build a report.
My goal is to see only "Milestone" tasks (of any status), but only when the Parent Status is "in-progress".
I can't seem to find the right combination of filters to build this report? Can you help?
thank you tons!
Tags:
Best Answer
-
You would need a helper column that brings the parent status onto each row. You would then filter the report by this helper column and the activity type column.
Answers
-
You would need a helper column that brings the parent status onto each row. You would then filter the report by this helper column and the activity type column.
-
Paul, you're a genius! Tell your boss to give you a raise!
worked like a charm!...
big thank you!!!