Calculating a date using a 'date' column and a 'number of days' column
Victoria Ganuelas
✭✭✭✭
I need a formula that takes a 'date' column and minus' the number in a 'number of days' column to show that calculated date in another date column.
Answers
-
Hello @Victoria Ganuelas
This should work:
=WORKDAY([Original Date]@row, -[Number of Days]@row)
Make sure the column type with the formula is set to Date.