I have inherited a project plan/Gantt chart that has a "Critical" column with the ISCRITICAL formula
Would appreciate any help. Thanks!
Answers
-
I have inherited a project plan/Gantt chart that has a "Critical" column with the ISCRITICAL formula. However, I don't know how to flag a task so it becomes critical. How do I update a task to be considered critical on my Gantt chart?
-
It is based on predecessors and whatnot. If a delay on that specific task directly affects the projected end date based on the predecessors in the tasks that come after, it is automatically considered critical. You can use the ISCRITICAL function to output something based on whether it is or not, but you can't use a formula or anything to change whether or not it is.
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
-
Thank you Paul!!!
-
Happy to help. 👍️
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 379 Global Discussions
- 213 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 305 Events
- 34 Webinars
- 7.3K Forum Archives