hi i have 2 types of Start and End date.
i have Actual start date, Actual End date and Actual Duration.
also, i have Planned Start Date, Planned End Date, and Variance (for Baseline).
the Actual duration is the duration of the task based on the Actual start & Actual End date.
what i want is to be able to calcuate a Planned Duration (a duration based on the Baseline Dates). **Not (Planned End date - Planned Start Date))
how to do it? is there a formula?
Also, in the Variance Column, it is Unparsable, why?
please help thank you!