Variance Column Unparseable

Options

hi i have 2 types of Start and End date.

i have Actual start date, Actual End date and Actual Duration.

also, i have Planned Start Date, Planned End Date, and Variance (for Baseline).

the Actual duration is the duration of the task based on the Actual start & Actual End date.

what i want is to be able to calcuate a Planned Duration (a duration based on the Baseline Dates). **Not (Planned End date - Planned Start Date))

how to do it? is there a formula?

Also, in the Variance Column, it is Unparsable, why?

please help thank you!


image.png


Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!