Critical chain
I would like to know if when working in a timeline with Smartsheet, if there is an option to choose critical chain vs critical path? And if that is possible, if it also builds the fever chart.
Thank you,
Answers
-
Hi @noviceuser
As you've found, Smartsheet has a Critical Path, as well as a Summary and Driving path in a Project Sheet with dependencies enabled (see here). You can build out a Critical Chain type of project in Smartsheet but what will be highlighted in the Gantt view will be the Path.
Smartsheet does not have an automatic buffer fever chart, but you may be able to create this with your own data depending on how your sheet/project is set up. I see you already submitted a request for this type of chart in the Product Ideas area, thank you!
If you're looking to focus more on resources versus tasks, you may want to check out Resource Management by Smartsheet and the panel that links these two platforms together.
Cheers,
Genevieve
Join us for Jumpstart 2025 with Community on 23 January (in two time zones)! 🎉 Register here.
-
@Genevieve P. Has there been any progress on the fever chart? Also - could you point me to a tutorial for Critical Chain in Smartsheets?
Thanks
-
Hi @Taraneh F
Please feel free to add your vote and voice to the related Product Idea! Our Product team reviews ideas that come in and provides a status update if it's a top-voted post each month.
Join us for Jumpstart 2025 with Community on 23 January (in two time zones)! 🎉 Register here.
-
Already did - just wanted to see if there was any movement on this.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.2K Get Help
- 445 Global Discussions
- 143 Industry Talk
- 476 Announcements
- 5K Ideas & Feature Requests
- 84 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives