Time Line Chart Query
Hello Experts,
I need to build a time-line chart with Planned Vs Executed comparission. Possibly the count would be the Test ID count. Status is fine.
How can I achieve this solution in the Dashboard?
Tags:
Answers
-
Hi @tamiz.vedachalam Dashboard charts don't support date data. You could get creative with a Gantt view using baselines. Here is a help article about baselines: https://help.smartsheet.com/articles/2482093-baselines