Need Help with Formula to Roll Up and Average Schedule Health.
I have one that now updates the Schedule Health RYG based on the Start Date/End Date and Task Status.
Next, I am trying to roll up/average those Individual Task schedule health values to an overall Phase schedule health value and then ultimately to the Overall Project schedule health.
Current formula: Overall Project Schedule Health would never move from Green unless we were past the final End Date
Baseline model: Once you go red, you can never get back to green or even yellow
Any insight would be much appreciated.