Hello Community,
I need to link a cell to another cell (different sheet) and also add extra number of days to the value in the cell. What is the best way to go about this.
The cells are dates, for example
Sheet 1 has cell A = 12/05/23 needs this cell needs to be imported to Sheet 2 cell B plus 10 days.
Best Answer
-
In that case you would need to create the cell link in one column and then add then days with a cell reference to the linked cell in another column.
Answers
-
Is there a unique identifier on the row in both sheets we can use to match them together, or are you wanting to just pull in a direct cell link?
-
There is no identifier, I just want to pull the cell link and add extra number days to it in the other cell in a different sheet.
-
In that case you would need to create the cell link in one column and then add then days with a cell reference to the linked cell in another column.
-
Thanks, I thought about that too but was wondering if there is a better way to get it done. Thanks Paul much appreciated.
-
Happy to help. 👍️
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.1K Get Help
- 444 Global Discussions
- 140 Industry Talk
- 472 Announcements
- 5K Ideas & Feature Requests
- 83 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 497 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 35 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!