How Come All of My Tasks Aren't Getting Dependencies?
Mila S.
✭✭
Hi,
I don't get it. I'm trying to make a Dependencies column for my projects, but it didn't register all of the tasks that I have on the sheet. (Reference pic below). Why is that?
Answers
-
Hi,
You need to fill in the predecessor column. Example: For row 6, if the dependency is row 5, you need to fill the predecessor in row 6 as "5". Also, make sure the dependencies is enabled in your smartsheet schedule project setting.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.9K Get Help
- 441 Global Discussions
- 153 Industry Talk
- 501 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 155 Just for fun
- 79 Community Job Board
- 511 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 37 Webinars
- 7.3K Forum Archives