How Come All of My Tasks Aren't Getting Dependencies?

Hi,

I don't get it. I'm trying to make a Dependencies column for my projects, but it didn't register all of the tasks that I have on the sheet. (Reference pic below). Why is that?


Answers

  • Shanky Paul
    Shanky Paul ✭✭✭✭✭

    Hi,

    You need to fill in the predecessor column. Example: For row 6, if the dependency is row 5, you need to fill the predecessor in row 6 as "5". Also, make sure the dependencies is enabled in your smartsheet schedule project setting.