Hello - What's the minimum level of access to grant for an assigned to to update just task % complete & status? Do not want them having access to change anything else in the project plan.
Best Answer
-
Editor access, but you can lock columns. Update requests can also be sent and means that users do not have any access at all to the sheet.
Answers
-
Editor access, but you can lock columns. Update requests can also be sent and means that users do not have any access at all to the sheet.
-
Thanks, Paul.
-
Happy to help. 👍️