Minimum level of access for an assigned to to update task % complete & status
jmacdal
✭✭✭
Hello - What's the minimum level of access to grant for an assigned to to update just task % complete & status? Do not want them having access to change anything else in the project plan.
Best Answer
-
Editor access, but you can lock columns. Update requests can also be sent and means that users do not have any access at all to the sheet.
Answers
-
Editor access, but you can lock columns. Update requests can also be sent and means that users do not have any access at all to the sheet.
-
Thanks, Paul.
-
Happy to help. 👍️
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 495 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives