Is it possible to dynamically add triggers from Smartsheet to a bridge workflow?
I have finally gotten my first bridge to Smartsheet workflow working. My workflow copies project plan baseline dates to an original baseline field the first time a baseline is set, and then will not set it again.
This works when I manually setup a trigger in bridge for a specific project plan sheet. However, I have 75 projects provisioned via control center and I don't want to have to manually setup a new trigger when each project gets provisioned. I would like those triggers to be dynamic if possible.
Is there any way to achieve this?
Best Answer
-
Since I don't think there is a way to do this currently, I went a different direction and setup a trigger to run daily and get a handle to the workspace that we provision all projects to, iterated through the list of folders, iterated through the sheets to identify the project plans, and continued the logic from there.
Would be nice to have a feature that enables provisioning triggers to new projects via Control Center.
Answers
-
Since I don't think there is a way to do this currently, I went a different direction and setup a trigger to run daily and get a handle to the workspace that we provision all projects to, iterated through the list of folders, iterated through the sheets to identify the project plans, and continued the logic from there.
Would be nice to have a feature that enables provisioning triggers to new projects via Control Center.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 136 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 485 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives