Heath Status Symbol - Parent Row Setup
Hey Guys,
Brand new user here trying to understand the correct formula for a simple project health status.
Have new project where all children roll up to one parent row with start date, end date & % complete.
Would like to have a simple Red, Yellow & Green symbol based upon the parent row that shows overall project status based upon the parent Start , End Date & % Complete.
Can anyone help me in understanding how to set this up?
Hope this makes sense.
Thank you in advance !
Samual
Best Answer
-
Try this:
=IF([% Complete]@row = 1, "Blue", IF([Due Date]@row< TODAY(), "Red", IF([Due Date]@row<= TODAY(10), "Yellow", "Green")))
Answers
-
So you want all of the child rows to match the parent row RYG? What would be the logic for populating the parent row RYG?
-
Hi Paul,
We just want the child rows to roll up the overall % Complete for the parent which they do.
Now I'm just looking for the RYG status for the parent overall % Complete to reflect the status of the project at a high level . We might add to all the children rows at a later time for more detail.
Thanks for the help !
Sam
-
If everything is rolling up then you should be able to apply a column formula so that every row is based on the criteria you are wanting for the RYG.
-
Hey Paul,
Here's what I'm looking for below, correct me if my logic is backwards. I looked at some examples and modified them to get parse errors.
· COMPLETE - Blue: % Complete is 100% regardless of the date.
· PAST DUE - Red: Today’s Date is 1 day after Due Date AND % Complete is < 100%
· Behind - Yellow: Today’s Date is 10 before Due Date AND % Complete is < 75%
· On Track - Green: Until its hits the Behind Yellow above.
Thanks for your help.
Sam
-
Try this:
=IF([% Complete]@row = 1, "Blue", IF([Due Date]@row< TODAY(), "Red", IF([Due Date]@row<= TODAY(10), "Yellow", "Green")))
-
That worked !
Thank You
Sam
-
Hey Paul,
The formula worked, how can we modify it so that when the % complete is below 75% within 10 days shows behind, other wise anything above 75% shows on track regardless of the 10 day count?
-
So you want what exactly? Yellow only if within 10 days and less than 75%. If it is 76% and due tomorrow, it still shows green?
-
Hey Paul,
Not thinking through the process enough, the formula you provided will get us there.
Thank you again for ur help!
Sam
-
Hi Paul,
Could you look at the formula below and tell me what I missed, getting error.
Trying to get : Complete , Not Started , In Progress & Past Due
=IF([% Complete]@row >= 1, "Complete", IF(OR([% Complete]@row = "", [% Complete]@row
= 0), "Not Started", "In Progress", IF[TODAY() > [Due Date]@row, "Past Due")))
Thank You
Sam
-
Try this:
=IF([% Complete]@row = 1, "Complete", IF([Due Date]@row< TODAY(), "Past Due", IF([% Complete]@row> 0, "In Progress", "Not Started")))
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!