Gantt chart issue

ramazurjr
✭✭
I'm on a trial basis. I entered all my Tasks/Descriptions/Dates, etc and they look good in Grid view. However, when I switch to Gantt, one one of them runs across a variety of due dates. I'm sure I'm missing something
Best Answer
-
I believe the problem is row # 7 has a Start Date with the year of 2013 instead of 2023.
Answers
-
Hi @ramazurjr,
Would you mind posting a screenshot of the issue, and one of the grid?
-
I believe the problem is row # 7 has a Start Date with the year of 2013 instead of 2023.
-
Fat fingers will do that!