Multiple Resources Assigned to Task -Shouldn't this Change Finish Date?
I have a project I'm working on and when I add resources to tasks it does not change the finish date? Is this normal? Is there anything I can do to change it? Settings? Resource Management?
Help!
Answers
-
@AriZ Can you put some screen shots.
-
Sure - so in the screenshot I'm attaching there are a few lines with tasks that have
a. start date
b. finish date
c. desired finish date
d. assigned resources with % allocation
The lines that have multiple resources originally had only 1 resources, but I added another in an effort to change the finish date. Nothing happened.
Additionally, when you add a second resource, there is no way to assign a separate allocation %.
-
Hi @AriZ
I hope you're well and safe!
If you're using the Resource Management feature, add each resource on a separate row
Did that work/help?
I hope that helps!
Be safe, and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 494 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives