Gantt off by 1 year

Hello, I am having an issue where one of my tasks is off by 1 year when I open up the Gantt View. Please see the attached screenshot of this issue. I cannot figure out why this is happening. Thanks.
Best Answer
-
Hello, @Kurt T.,
I just tested with my primary Gantt heading as "Year", and my secondary heading as "Month". Also updated my Fiscal Year to start with April as you have yours.
Mine resulted in appearing to be 1 year late on the Gantt chart too. I made 2 entries to demonstrate.
If nobody chimes in with a reason or explanation, I would report this to Smartsheet as a potential bug/defect.
Answers
-
Hello, @Kurt T.,
I just tested with my primary Gantt heading as "Year", and my secondary heading as "Month". Also updated my Fiscal Year to start with April as you have yours.
Mine resulted in appearing to be 1 year late on the Gantt chart too. I made 2 entries to demonstrate.
If nobody chimes in with a reason or explanation, I would report this to Smartsheet as a potential bug/defect.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.1K Get Help
- 430 Global Discussions
- 149 Industry Talk
- 490 Announcements
- 5.2K Ideas & Feature Requests
- 85 Brandfolder
- 154 Just for fun
- 74 Community Job Board
- 499 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 305 Events
- 36 Webinars
- 7.3K Forum Archives