Update Status Column based % Complete, Finish Date and Today
Hi,
I am trying to work out the correct formula so my Status Column updates automatically based on % Complete, Finish and Today's date.
I am using this formula for the Progress Column:
=IF(Status@row = "At Risk", "Red", IF(Status@row = "Pending", "Yellow", IF(Status@row = "In Progress", "Green", IF(Status@row = "Complete", "Blue"))))
But I am unable to land on the correct formula for the Status Column.
Thank you
Best Answer
-
Line 6 wouldn't be at risk because it is not less than 50% complete.
Line 8 SHOULD be at risk based on the formula. How exactly are you populating the dates?
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
Answers
-
Hi @Jacquita
Please specify the logic you are looking to implement to decide At Risk, Pending, In Progress, and Complete.
Thanks,
Aravind GP| Principal Consultant
Atturra Data & Integration
M: +61493337445
E:Aravind.GP@atturra.com
W: www.atturra.com
-
Hi Aravind,
Thanks for reaching out.
Basically I want the Status categories to be automated based on % Complete against Today's date and the Finish date.
I thought I had it with this formula below, but every entry comes back as Pending.
And if I put a future date in Start Date, I get INVALID OPERATION.
=IF([% Complete]@row = 1, "Complete", IF(AND([% Complete]@row < 1, [Finish Date]@row < TODAY()), "Pending", IF(AND([% Complete]@row < 0.5, [Finish Date]@row < =TODAY(5)), "At Risk", IF(AND([% Complete]@row < 1, [Finish Date]@row > TODAY(7)), "In Progress", ""))))
-
Try this:
=IF([% Complete]@row = 1, "Complete", IF([Finish Date]@row< TODAY(), "Pending", IF(AND([% Complete]@row< 0.5, [Finish Date]@row<= TODAY(5)), "At Risk", "In Progress")))
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
-
hi Paul,
Many thanks for your help, that has got me closer.
A few questions please re example attached:
Row 2 - should be At Risk?
Row 3 - should be At Risk?
Row 6 - shows In Progress, but is not started (i.e )%).
Thank you
-
Try this:
=IF([% Complete]@row = 1, "Complete", IF(AND([% Complete]@row< 0.5, [Finish Date]@row<= TODAY(5)), "At Risk", IF([Finish Date]@row< TODAY(), "Pending", "In Progress")))
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
-
Brilliant thanks Paul.
-
A couple of queries, using the formula above:
Line 6 should be At Risk
I think Line 8 should be At Risk also?
thank you
-
Line 6 wouldn't be at risk because it is not less than 50% complete.
Line 8 SHOULD be at risk based on the formula. How exactly are you populating the dates?
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
-
Got it Paul, an error my end. Appreciate your help and persistence.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 380 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 305 Events
- 34 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!