Duration column chart for a dashboard
Hey,
I am trying to build a chart that shows me the duration of the tasks. I would like this to be a bar chart, so i can see how long each task took in comparison (these are the same tasks in different projects that take people different amount of time).
I am unable to use a report that shows the primary column and the duration column, that is auto calculated for the gantt chart. Am I missing something? Do I need another column that calculates the duration with a formular?
Thanks a lot !
Answers
-
Whenever mapping out data I always try to create tables.
In this instance, what I would do is create my own table and it would look something like this:
Column names
Task | Duration (Value of duration in hours or days)
Cell data
task name | value
now you can map task name to y, and the value to x via chart on dashboard.
Sincerely,
Jacob Stey
-
Hi @NeuerNutzer
If you set "dependency enabled" at the Project Settings, which you usually will do, you can not use the duration column in the dashboard chart widget.
So, as you wrote above, You "need another column that calculates the duration with a formula."
The formula is straightforward, though.
Example:
Duration (In Days) = Duration@row
Then, you can use this value to create a chart.
The example below uses Report as the Chart source, whose base sheet uses conditional formatting to highlight durations greater than 7.
As you mentioned, you can not remove or hide a primary column in a report, but it acts like a Bar chart's series label.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.9K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 440 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 284 Events
- 33 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!