Hi everyone,
We have a project plan sheet for each of our projects containing a long list of tasks. My predecessor made 3 columns for counting number of Total Tasks, Tasks Completed, and Tasks Overdue.
I recently made some graphs using this data and noticed that the numbers were off, and I need some help in changing the formulas.
It seems that the count for 'Task Completed' dosen't atually count if the checkbox for 'Task Complete' is checked, but rather triggers if the checkbox is checked and today is past the deadline, which seems redundant. Additionally, I feel the other formulas can be simplified: maybe Total Tasks could be a single formula, instead of running in each cell? I also hope to avoid using TODAY altogether, as it ruins the data in the column checking for changes.
The current formulas are as follows and are in each cell down the columns.
Tasks Total: =COUNT([Task Complete?]164:[Task Complete?]164)
Completed tasks: =COUNTIFS(Finish164:Finish164; <TODAY(); [Task Complete?]164:[Task Complete?]164; 1)
Tasks overdue: =COUNTIFS(Finish164:Finish164; <TODAY(); [Task Complete?]164:[Task Complete?]164; 0)
So, to sum up, can anyone help me with how to write these 3 so they are more optimized to the above? 😊