If my project is assigned to the resource base on ROLE, how can we auto-populate the assigned to in Smartsheet when we also need to sync with Resource Management?
For example: for Project A
Architect: A person, Project Manager: B person, Designer: C person
    
        
             
    
For the above, I can have Sheet B with Role and Name for this project.  All the roles are predefined base on task.  I just need to update the Role and Name in Sheet B and my project sheet will be updated accordingly.
I am also using Resource Management, but I find that I can't sync this Assigned2 column with Resource Management.  We will have to manually assign the role for each task.
How can we auto-populate the assigned to in Smartsheet when we also need to sync with Resource Management?