elapsed time duration
Jamie Cope_Tempest
โญโญ
This has been requested for years. Standard in MS Project. Need to allow for task-specific 7day workweek in projects that are set to 5-d work weeks. Common for projects imported from MS Project to SmartSheet.
Answers
-
You can use elapsed time in the duration field by adding an e in front of the duration:
Here's more information: Workย with Duration and Predecessors
Cheers,
Genevieve
Need more information? ๐ | Help and Learning Center