Start date on task and predecessor links
Hello, when I modify a start date on a task I lose the predecessor links. Is there a method to modify task start dates without losing the links?
THANKS.
Best Answer
-
Hi @Loic
If you need to change a Start date while keeping the Predecessor, then you'll either need to change the Predecessor date or add Lag / Lead time to the dependent task.
Here's more information on Lag and Lead time: Work with Duration and Predecessors
Cheers,
Genevieve
Join us for Jumpstart 2025 with Community on 23 January (in two time zones)! 🎉 Register here.
Answers
-
Hi @Loic
If you need to change a Start date while keeping the Predecessor, then you'll either need to change the Predecessor date or add Lag / Lead time to the dependent task.
Here's more information on Lag and Lead time: Work with Duration and Predecessors
Cheers,
Genevieve
Join us for Jumpstart 2025 with Community on 23 January (in two time zones)! 🎉 Register here.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.2K Get Help
- 445 Global Discussions
- 142 Industry Talk
- 473 Announcements
- 5K Ideas & Feature Requests
- 84 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 489 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives