Start date on task and predecessor links
Hello, when I modify a start date on a task I lose the predecessor links. Is there a method to modify task start dates without losing the links?
THANKS.
Best Answer
-
Hi @Loic
If you need to change a Start date while keeping the Predecessor, then you'll either need to change the Predecessor date or add Lag / Lead time to the dependent task.
Here's more information on Lag and Lead time: Work with Duration and Predecessors
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Answers
-
Hi @Loic
If you need to change a Start date while keeping the Predecessor, then you'll either need to change the Predecessor date or add Lag / Lead time to the dependent task.
Here's more information on Lag and Lead time: Work with Duration and Predecessors
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.6K Get Help
- 433 Global Discussions
- 136 Industry Talk
- 466 Announcements
- 4.9K Ideas & Feature Requests
- 143 Brandfolder
- 147 Just for fun
- 64 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 298 Events
- 36 Webinars
- 7.3K Forum Archives