Start date on task and predecessor links
Hello, when I modify a start date on a task I lose the predecessor links. Is there a method to modify task start dates without losing the links?
THANKS.
Best Answer
-
Hi @Loic
If you need to change a Start date while keeping the Predecessor, then you'll either need to change the Predecessor date or add Lag / Lead time to the dependent task.
Here's more information on Lag and Lead time: Work with Duration and Predecessors
Cheers,
Genevieve
Join us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now
Answers
-
Hi @Loic
If you need to change a Start date while keeping the Predecessor, then you'll either need to change the Predecessor date or add Lag / Lead time to the dependent task.
Here's more information on Lag and Lead time: Work with Duration and Predecessors
Cheers,
Genevieve
Join us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.8K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 438 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 451 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 282 Events
- 32 Webinars
- 7.3K Forum Archives