Start date on task and predecessor links

Hello, when I modify a start date on a task I lose the predecessor links. Is there a method to modify task start dates without losing the links?
THANKS.
Best Answer
-
Hi @Loic
If you need to change a Start date while keeping the Predecessor, then you'll either need to change the Predecessor date or add Lag / Lead time to the dependent task.
Here's more information on Lag and Lead time: Work with Duration and Predecessors
Cheers,
Genevieve
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
Answers
-
Hi @Loic
If you need to change a Start date while keeping the Predecessor, then you'll either need to change the Predecessor date or add Lag / Lead time to the dependent task.
Here's more information on Lag and Lead time: Work with Duration and Predecessors
Cheers,
Genevieve
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.8K Get Help
- 474 Global Discussions
- 207 Use Cases
- 517 Announcements
- 5.5K Ideas & Feature Requests
- 87 Brandfolder
- 157 Just for fun
- 83 Community Job Board
- 521 Show & Tell
- 36 Member Spotlight
- 3 SmartStories
- 309 Events
- 37 Webinars
- 7.3K Forum Archives