Hello,
How can I get the gantt task label to show up in my dashboards when using the report widget? I have it turned on in the sheet settings.
Note, I cannot use the web content widget because I am using that to display a calendar view of the timeline.
Thanks
Oliver
Answers
-
Hi @Oliver P
You need to set the "Display Lable for" value in the "Project Setting" of a report.
I found, answering your question, that the "Display Lable for" settings in the source sheet and reports are independent. This makes sense since a report can have multiple source sheets with different "Display Lable for" settings. Regardless of the setting at the source sheets, the report's setting prevails.
-
So, even if you "have it turned on in the sheet settings.", you still need to turn it on in your report.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.7K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 438 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 451 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 282 Events
- 32 Webinars
- 7.3K Forum Archives