How to auto compute the task Status based on the task and predecessors % Completion status
The snapshot is my sample Project Plan.
From this data table, appreciate if the expert can help me to derive the Status column formula based on the following remark:
1. Status column with the status Not Started is the % Complete equal to 0%.
2. Status column with Complete is when % Complete archive 100%.
3. Status column with Ready to start is when all Predecessors % Complete achieve 100% in example task in row 12.
4. Status column with the status In Progress is when % Complete in between above 0% and less than 100%.
I would appreciate, if anyone has developed or encountered any suitable solution for the above.
Thank you.
Answers
-
to conclude this question, I have found the solution for the above as per this link https://community.smartsheet.com/discussion/114937/status-with-predecessor#latest
Credit to @jmyzk_cloudsmart_jp for the support.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.3K Get Help
- 364 Global Discussions
- 200 Industry Talk
- 428 Announcements
- 4.4K Ideas & Feature Requests
- 136 Brandfolder
- 129 Just for fun
- 128 Community Job Board
- 446 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 283 Events
- 35 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!