I need to have a formula for my Completion Status column. Here are the criteria and the screenshots. I keep failing at trying to write this formula, so I would appreciate some assistance. thanks in advance for your help!!
- The formula and all cells referenced are on the SAME sheet
- The formula is being written in the "Completion Status" column (screenshot 2)
- There are 3 potential Statuses for this column:
On-time - Completed prior to "Target Implementation Date" (screenshot 1). "Status" (screenshot 2) column is marked as Complete when a date is entered into "Actual Implementation Complete Date" (screenshot 1) is before "Target Implementation Date" (screenshot 1).
Complete Past Due - "Actual Implementation Complete Date" is after Target Implementation Date.
Past Due - If the "Status" column does NOT show as "Complete" yet ("Actual Implementation Complete Date" is blank), and the Target Implementation Date has passed.
In Progress - And all others should show the in progress status. So that would be 4 statuses altogether.