Change the dates on my Gantt chart with dependencies
Roy Cordell
✭✭
I know I'm being stupid, but I can't for the life of me figure out how to change the end date of a Gantt chart I've created. Dependencies are enabled.
Tags:
Answers
-
Hey @Roy Cordell
There are no stupid questions! 🙂
Is it possible that the End Date is part of a Parent row? If so, you'll need to adjust the end date of the latest Child Row to push out the Parent date (see: Parent rollup functionality)
If that hasn't helped, can you post a screen capture of the row you're trying to adjust? But please block out sensitive data.
Thanks,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives