Change the dates on my Gantt chart with dependencies
Options
Roy Cordell
✭✭
I know I'm being stupid, but I can't for the life of me figure out how to change the end date of a Gantt chart I've created. Dependencies are enabled.
Tags:
Answers
-
Hey @Roy Cordell
There are no stupid questions! 🙂
Is it possible that the End Date is part of a Parent row? If so, you'll need to adjust the end date of the latest Child Row to push out the Parent date (see: Parent rollup functionality)
If that hasn't helped, can you post a screen capture of the row you're trying to adjust? But please block out sensitive data.
Thanks,
Genevieve