Project Plan...3 questions
Hello team - I realized I posted this in discussions instead of questions. Couldn't figure out why noone answered :)
Also, is anyone having issues using templates from smartsheet website? I have been fine all day but now they are not linking and I don't know why. Thank you in advance!
Best Answers
-
Hi @Michele R.
- You can add actual start and end dates and have the flags reference these columns. If a formula already exists, replace the names of the columns from Start Date to Actual Start Date, and the same for the end date once you've created the columns
- Your % complete in the parent is not showing any data as the place where 100% appears has 0 days as duration. The parent row auto calculate the % complete based on the % complete entered in the child rows and their corresponding duration in relation with the overall duration for the parent. For example, if you've three tasks with 3 days each. Your parent will have a duration of 9 days. Once you've one of the tasks marked as 100%, the parent row will calculate 3 days completed of 9 days, so 33%.
- When you add a date, Smartsheet will consider it to be 1 day when the start and end dates are the same. There's no automated way to make the first days as 0 duration.
Thanks,
Aravind GP| Principal Consultant
Atturra Data & Integration
M: +61493337445
E:Aravind.GP@atturra.com
W: www.atturra.com
-
Thank you!
Answers
-
Hi @Michele R.
- You can add actual start and end dates and have the flags reference these columns. If a formula already exists, replace the names of the columns from Start Date to Actual Start Date, and the same for the end date once you've created the columns
- Your % complete in the parent is not showing any data as the place where 100% appears has 0 days as duration. The parent row auto calculate the % complete based on the % complete entered in the child rows and their corresponding duration in relation with the overall duration for the parent. For example, if you've three tasks with 3 days each. Your parent will have a duration of 9 days. Once you've one of the tasks marked as 100%, the parent row will calculate 3 days completed of 9 days, so 33%.
- When you add a date, Smartsheet will consider it to be 1 day when the start and end dates are the same. There's no automated way to make the first days as 0 duration.
Thanks,
Aravind GP| Principal Consultant
Atturra Data & Integration
M: +61493337445
E:Aravind.GP@atturra.com
W: www.atturra.com
-
Thank you!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.9K Get Help
- 379 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 301 Events
- 33 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!