Project completion T-minus date

Hello - Thank you in advance

Requesting a column formula in my project sheet.

I have a "Project completion" date as well as tasks that work back by week (can be days if easier). I would like to be able to enter any "Project completion" date and ensure the tasks change based on that date.

IE: Project completion is August 12th and Task A has to be completed 4 weeks earlier I would like the task to show a start date of September 12th (or 30 days earlier)

Best Answer

  • Paul Newcome
    Paul Newcome ✭✭✭✭✭✭
    Answer ✓

    I would suggest relocating to a sheet summary field so that you can make it a column formula.

    When using a number of days, it is a simple subtraction.

    =[Launch Date]# - [T-Days]@row

    Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!

    CERTIFIED SMARTSHEET PLATINUM PARTNER

    10xViz.com

Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!