Strikethrough dates

vsivasailam
✭✭
Hi,
How can I show a strikethrough date in Smartsheet? Essentially I want to show that the original end date has moved to a new end date and would like to show the original end date to be striked off.
Regards,
Vivekram
Answers
-
Are you able to provide some screenshots for context?
-
Something like this. Where you have the planned (or the original date set). In the projected you strike out previously suggested dates as shown above.
-
You would have to have each date in a separate cell.
-
ahhh okay