Is percent complete only available in a paid version?

Doug Taylor
ββ
Is percent complete only available in a paid version?
Answers
-
Hi Doug,
A user with Admin or Owner permissions on a sheet can set that up when the Gantt view is on and they enable dependencies for a project.
In order to have those permissions, you need a paid license. You can ask whoever created or has admin permissions to the sheet you are working on to set this column up for you.
This article explains how to get started: https://help.smartsheet.com/articles/765737-project-sheet-columns-start-date-end-date-duration-complete-and-predecessors#toc-enable-dependencies