Formula for calculating overlapping dates for approval tasks
I am trying to find a way to properly calculate how long an approval takes from an outside source. Is there a formula or a workflow that can take overlapping dates and give the correct answer? I also need the formula to be able to update if the initial start date gets pushed out.
I have attached an image of the date layout. If the dates overlap (for example 1/11/24 - 2/21/24 and 1/12/24-1/12/24 have a day overlap so the total would be 30 days not 31). I can clarify if needed.
Answers
-
Are you using the dependency settings in the sheet?
-
@Paul Newcome yes, I believe so.
-
Have you tried setting up predecessors?
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.3K Get Help
- 445 Global Discussions
- 143 Industry Talk
- 477 Announcements
- 5K Ideas & Feature Requests
- 85 Brandfolder
- 150 Just for fun
- 72 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 302 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!