Resources and Duration
I would like to make the “Duration” column dependant on the hours needed and the team assigned to develop a task; something like “Hours (quoted) / Team (number of people)= Duration”. Is that possible? How can I do it? Thank you for your guidance.
Comments
-
If Dependencies are enabled, you can't have a formula in the Duration (or other Project Settings related columns).
You can set up the Duration formula to get the results and then turn on Dependencies - it will keep the Duration but remove the formula.
What I do is create a second column to have my calculated duration and then copy that column's contents to the Duration column. I usually have another column to check if the two columns are different.
I hope that helps.
Craig
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 380 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 305 Events
- 34 Webinars
- 7.3K Forum Archives