Have you noticed smartsheet calculate wrong dates?
Hi,
There are some instances that SmartSheet calculates dates wrong. For example, row 7 dates (1st image) were calculated based on row 6 (2nd image). Note that, the correct row dates should be 24/02/24 to 27/02/2024.
Is there any explanation? Am I doing something wrong?
Cheers,
Mahfuz
Best Answer
-
Hello @uqmchow2
You should review your project settings, it appears that it's configured for a duration of 5 working days, excluding weekends.
Hope this helps
Che
Answers
-
Hello @uqmchow2
You should review your project settings, it appears that it's configured for a duration of 5 working days, excluding weekends.
Hope this helps
Che
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.7K Get Help
- 371 Global Discussions
- 205 Industry Talk
- 436 Announcements
- 4.5K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 129 Community Job Board
- 448 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 282 Events
- 32 Webinars
- 7.3K Forum Archives