Hi,
I am looking for some help with a formula that will calculate the number of days a project will be active in the year 2024. Below are the formulas I currently have plugged. I know that I need to embed something into the Duration Remaining column that will not count days past 12/31/2024.Yet, I am stuck.
Total Project Duration: =NETDAYS([Start Date]@row, [Finish Date]@row)
Total Remaining Duration: =IF([Start Date]@row <= [Today's Date]@row, [Finish Date]@row - [Today's Date]@row, [Total Project Duration Days]@row)
Duration Remaining - 2024: =IF([Total Remaining Duration]@row >= [Days Remaining In 2024]@row, [Days Remaining In 2024]@row, [Total Remaining Duration]@row)
Days Remaining in 2024: =Date@row - TODAY()
I do think I may have figured out a formula that works (see below).....but I know that there is something more simple than what I have come up with. I would like to have fewer columns.
Duration Remaining - 2024 r1 =IF([Start Date]@row >= Date@row, 0, [Duration Remaining - 2024]@row)
If someone can help me out that would be great!
Thank you