Assigned to Tasks not showing up in Card View
When I use the Card View to show by Assigned Owner, I see that no tasks are currently assigned to anyone even though the lanes show each owner:
The grid view looks as such:
Can anyone help me understand how to fix this? If I drag a card from the 'Uncategorized' column to one of the lanes for Assigned Owner, then it changes the Grid View cell for that task to be empty in the 'Assigned RA Owner' column.
Please help! :D
Answers
-
That is strange. Could you provide a screenshot of the column properties for "Assigned RA Owner"?
-
Were you ever able to resolve this? I'm having the same problem with a report. In grid view, everything is assigned to a contact. When I switch to card view, everything shows as uncategorized. And the list of people across the top doesn't even match those in the grid. Interestingly, I have several of these reports built out for various teams (all created from a copy) and some of the card views work as expected and some do not. Thanks for any help!
-Jackie
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 437 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives