Critical Path Won't Display
Hi, I have a sheet that refuses to display the red critical path. I've been up and down the sheet looking for missing links and parallel scope and I still can't figure it out. Can someone please help?
Answers
-
Hi @MzJones, do you have this button on?
-
Yes I do, and I've toggled it off and on and restarted the app to no avail
-
Hi @MzJones,
If your Project Setting's predecessors are linked as (finish-to-start), could you please try the following:
- Create a Checkbox type column named "Critical Task?"
- Apply column formula
=IF(ISCRITICAL([Task Name]@row), 1, 0)
This would identify tasks / rows with the longest distance between your start and finish dates. If you don't see any ticked checkboxes (you can also apply a filter to view and consolidate tasks on critical path), it may be something to do with your Project Settings setup. If all else fails, highly recommend Smartsheet's Project Tracking And Rollup template as a starting ground. Let me know how it goes!
Cheers,
Ric
-
is there a way to define the finish date instead of using the finish date of the entire project?
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives