Gantt chart - Milestones
PeggyLang
✭✭✭✭✭✭
Does anyone know what the 'empty' diamond means in a gantt chart?
Tags:
Answers
-
Hi @PeggyLang
It is used for Milestones. Smartsheet will tag something as a Milestone when the duration is 0.
Thanks,
Aravind GP| Principal Consultant
Atturra Data & Integration
M: +61493337445
E:Aravind.GP@atturra.com
W: www.atturra.com
-
In the screenshot the diamond filled in with black is actually the milestone for that task, the 'empty' milestone is actually the milestone associated with the predecessor. I'm wondering why there are two diamonds showing up on row 'Building Permit Received'.
-
I don't understand what all the lines to the right where I have noted with #'d icons. Does anyone know /can explain what they are there for?
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 138 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives