Gantt chart - Milestones

Options
PeggyLang
PeggyLang ✭✭✭✭✭

Does anyone know what the 'empty' diamond means in a gantt chart?


Tags:

Answers

  • AravindGP
    AravindGP ✭✭✭✭✭
    Options

    Hi @PeggyLang


    It is used for Milestones. Smartsheet will tag something as a Milestone when the duration is 0.

    Thanks,

    Aravind

    Reach out for any help on licenses, configuration, or training

  • PeggyLang
    PeggyLang ✭✭✭✭✭
    Options

    In the screenshot the diamond filled in with black is actually the milestone for that task, the 'empty' milestone is actually the milestone associated with the predecessor. I'm wondering why there are two diamonds showing up on row 'Building Permit Received'.

  • PeggyLang
    PeggyLang ✭✭✭✭✭
    Options

    I don't understand what all the lines to the right where I have noted with #'d icons. Does anyone know /can explain what they are there for?