Formula Variance Help
Good Afternoon. I am looking to set a Baseline Start and End date; however, I have several Phases that I would like to include to capture the change in phases. (i.e., prospecting how many days we have prospected a client and when the transition to implementation goes live. Etc. Is there a way to capture the movement in phases with the below formula as I keep getting the return of #UNPARSEABLE
Thank you!
=IFERROR(NETWORKDAYS([Actual Finish Date]@row, [Baseline Finish Date]@row), "Prospecting")
Answers
-
@KPH Apologies, but I have one additional query and wanted to see if I could get your assistance or thoughts. Much appreciated!
-
Are both of the Date columns set up as Date Type?
-
Yes, they are both set up as date columns, and the "prospecting" column is set up separately
-
@kph any thoughts? Thanks Much Appreciated!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.2K Get Help
- 445 Global Discussions
- 143 Industry Talk
- 476 Announcements
- 5K Ideas & Feature Requests
- 84 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!