How to plot multiple go live dates

Hello

We have some projects within our sheets and reports that have multiple go live dates for different offices. Is there a way to show the different dates without have multiple go live date columns? We want these dates to show on the GANTT Chart.

Thanks

L

Answers

  • Jake Kenyon
    Jake Kenyon ✭✭✭✭

    Could you add multiple lines to the project plan to account for the different go-live dates and label them accordingly? This is generally what I do when need to account for different go-live dates and would allow you to see those dates on the Gantt chart.