Simple Planned vs Actual Completion Formula
Hi all,
Trying to solve a quite simple problem with some most of the work already done.
I'm trying to show in a dashboard the percentage of tasks which should have been completed based on planned finish, vs the actual tasks completed.
I have a "Planned Finish" column, a "Status" and "Actual Completion Date" column. I intend to use a formula in sheet summary which I can then report on in the dashboard.
My assumption is this will be involve a combination of COUNTIF, TODAY and division, but I can't get my head round it.
Any help appreciated. Thanks
Answers
-
=COUNTIF([status]:[status]="complete"/COUNTIF([planned finish]:[planned finish]<TODAY())
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 380 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 305 Events
- 34 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!