Can we update the colors in grant view based on status values? All our reports , grant views should show the following. Appreciate any help.
Status Value - Color
In Progress - Green
Completed - Blue
Not Started - Gray
Answers
-
The "task bar" setting in conditional formatting will modify the "gantt bar" color.
-
Yes. Thank you.