How do I baseline new activities added to my schedule without it impacting the baselines already established for activities that had been in the schedule?
My schedule is being populated in phases so new activities will be added over time. If I reset the baselines already established for work that was in the plan already, it resets those baselines and I cannot see the variance anymore.
Tags:
Answers
-
You won't be able to use the Baselining feature for this.
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.8K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 440 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 284 Events
- 33 Webinars
- 7.3K Forum Archives