Imported Project % Completion Issue
Options
barmach
✭
I imported a MS Project Plan and the % complexation numbers are off in the Smartsheet version.
The project has five phases and each phase is a few points off. However the overall % completed is way off. MS Project shows 52% , Smartsheets 39%
Thoughts?
Answers
-
Hi @barmach
The percent complete may be using a different formula in Smartsheet than what was in your MS plan. Parent rows in project sheets roll up a percentage based on the child row percentages below and the duration of those child rows. Here's an article that explains the Parent rollup functionality.
Cheers,
Genevieve