Imported Project % Completion Issue
barmach
✭
I imported a MS Project Plan and the % complexation numbers are off in the Smartsheet version.
The project has five phases and each phase is a few points off. However the overall % completed is way off. MS Project shows 52% , Smartsheets 39%
Thoughts?
Answers
-
Hi @barmach
The percent complete may be using a different formula in Smartsheet than what was in your MS plan. Parent rows in project sheets roll up a percentage based on the child row percentages below and the duration of those child rows. Here's an article that explains the Parent rollup functionality.
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives