Imported Project % Completion Issue

barmach
✭
I imported a MS Project Plan and the % complexation numbers are off in the Smartsheet version.
The project has five phases and each phase is a few points off. However the overall % completed is way off. MS Project shows 52% , Smartsheets 39%
Thoughts?
Answers
-
Hi @barmach
The percent complete may be using a different formula in Smartsheet than what was in your MS plan. Parent rows in project sheets roll up a percentage based on the child row percentages below and the duration of those child rows. Here's an article that explains the Parent rollup functionality.
Cheers,
Genevieve
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67K Get Help
- 442 Global Discussions
- 154 Industry Talk
- 502 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 79 Community Job Board
- 512 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 307 Events
- 36 Webinars
- 7.3K Forum Archives