I have a high-level understanding of the various permission levels of Smartsheet. Since my project team is new to using Smartsheet, I'll be creating, editing and maintaining the sheets, reporting and dashboards for our project.
As using Smartsheet is new to my project team, I want to be cognizant about what permission level to provide them. My concern is that I don't want them to have access to modify the structure (adding/deleting columns and rows), but I do want them to be able to update their assigned tasks (ie. updating % complete). Thus, they need more than "Viewer" access. I assume they also need more than "Commenter" access since this still doesn't allow my team to edit the content within the sheet. However, "Editor" access is too much b/c then it does give them the ability to add/delete columns/rows (concern is that they'd add/delete rows/columns, and that could really mess up the project plan).
What is the best permission level to provide? Am I overlooking anything?