Update % COMPLETE based on another column

Options

I have an IF() that I am running to calculate a % complete of a tasklist. I want the % COMPLETE column to have the same value, so it will shade the bar in the gantt view. How do I do that?

I changed the settings for the "% complete column" to none to allow me to input a formula. However, it did not shade the bar (guessing this is the setting to define that shading).

I tried using an update automation, but it will only pass a string and not a formula.

Am I missing something? Is it not possible? Work around?

Answers

  • Andrée Starå
    Andrée Starå ✭✭✭✭✭✭
    Options

    Hi @Jared Agee

    I hope you're well and safe!

    Can you share some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help.

    I hope that helps!

    Be safe, and have a fantastic week!

    Best,

    Andrée Starå | Workflow Consultant / CEO @ WORK BOLD

    Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!

    SMARTSHEET EXPERT CONSULTANT & PARTNER

    Andrée Starå | Workflow Consultant / CEO @ WORK BOLD

    W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35

    Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.

  • Jared Agee
    Options

    Here you go... I want the values of the second column in the first.

  • Andrée Starå
    Andrée Starå ✭✭✭✭✭✭
    Options

    @Jared Agee

    Are you using the dependencies feature? If yes, you can't use a formula in the % Complete assigned in the project settings because it's automatic.

    Take into consideration that when you activate dependencies, you can't use formulas in the Start Date, End Date, Duration, % Complete, and Predecessors columns.

    Remember! Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up/Awesome or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!

    SMARTSHEET EXPERT CONSULTANT & PARTNER

    Andrée Starå | Workflow Consultant / CEO @ WORK BOLD

    W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35

    Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.

  • Jared Agee
    Options

    I changed the % Complete setting to none, which allows a formula. However, It does update the gantt.

    If I leave the setting above set to "% Complete" it will update that gantt but I have to manually enter the value.

    Is there not a way to keep the functionality to update the gantt and automate the entry of the value in the "% complete" field? I tried an automation, but it would not take the value from a cell (unless I am doing it wrong).

    Thanks for the insight and help.