Auto-calculate a date but round to nearest weekday
SallyJ
✭✭✭
I a creating a smartsheet that is calculating several milestone dates based on a single event date. This is the formula I'm currently using to calculate a milestone date 8 weeks prior to the event date, based on the event date being manually entered in the [Milestone Date]16 cell. Is there a way to make this return the nearest weekday?
=[Milestone Date]16 - 56
Thanks!
Best Answer
-
Have you checked out the WORKKDAY function yet?
Answers
-
Have you checked out the WORKKDAY function yet?
-
Perfect, thank you!
-
Happy to help. 👍️
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!