Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Fixing a milestone date
Comments
-
HI all,
I was just asked about Constraints today by a manager who's being asked to create and manage milestone schedules for a large number of projects. The ability to set constraints is a significant requirement for this person.
Is there an update from Smartsheet on this feature request? If it's still in the voting stage, please add our vote -- Smartsheet users since 2011.
Thanks,
susan
-
Please add my vote for a hard deadline or un-moveable milestone date constraint. It's unreasonable to ask all users to reshape their mindset derived from years of working with other tools to do Start-To-Finish scheduled to create one.
-
This is a feature i'd really like to see also.
-
Add another vote here - we're hoping to move to smartsheets from more basic tools like basecamp and excel, but this is a deal breaker for us. Our public events can't be moved, even if we're behind.
-
Is this ever going to happen?
It seems that this has been a topic for > 2y 9mo.
-
I posted this original request. Given up waiting for it to happen
-
I'm trying to make the decision where to move our team's current software from MS project over to Smartsheet. I was really liking things until I discovered this issue.
The lack of response to this issue is scary!
Other users, is this a sign that they are not investing in the development of the platform? Have there been recent feature updates?
This is a key function for anyone who needs to build schedules to hit multiple milestones with dependencies. One is left with the options of removing dependencies or having your schedule go wonky because a team member improved 3 days on there task estimation.
I am thinking of creating paired milestones (one dependent, one fixed) and trying to figure out a way to highlight when the two don't match.
Can anyone else a suggest a hack around this?
Any updates from the product mgmt team @ smartsheet?
-
+1 on this one!
One of these small but important features that makes MS-project the go-to-tool when things need to work...
I vote that the majority of focus in development is pointed to answer the holy grail of project questions: "at what point is the sh*t hitting the fan?"
And I want the application to tell me that, I dont want to spend time looking for it line by line...
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 136 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 485 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives