IF Formula assistance.
Answers
-
Hi @Hollie Green, @Genevieve P. and @parulmishra, I need help with your formula. I'm using it on a project task management sheet. The issue is with tasks with start and end dates in the future. The result for these tasks is a negative percentage of completion. This affects my project's overall progress on the summary page, as it averages the percentages from each task. What is the best course of action to resolve this problem?
=IF(AND([End Date]@row <= TODAY(), Status@row <> "Complete"), 1, IF(Status@row <> "Complete", NETWORKDAYS([Start Date]@row, TODAY()) / NETWORKDAYS([Start Date]@row, [End Date]@row), 1))
-
You could simply wrap the whole think in another if statement that forces a 0 if the start date is greater than today(). That would likely be the simplest.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.3K Get Help
- 445 Global Discussions
- 144 Industry Talk
- 477 Announcements
- 5K Ideas & Feature Requests
- 85 Brandfolder
- 151 Just for fun
- 72 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 302 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!