Hello
I am trying to connect about 50 project plan sheets on one sheet. The requested configuration is a traffic indicator for a customer then the ability to drill down to see each customer project and status then a drill down for high-level milestones.
FYI I have just read about the limitations so I understand eventually we will reach the 5,000 cell limit.
I also see the customer traffic indicator will need a formula if they have more that one project which some do, as well as duration and start date.
I am able to link cells and show both customer and by project indicators however for some projects, when I indent, the percentages are not changed but for other projects and the one in the screenshot, the minute I start to indent to match the original source sheet the percentages start to change.
I am wondering about some of the parent child formulas and if there is something else I need to do for the destinations sheet to be aware of the high level true percentage w/o copying the whole sheet or is it maybe the set up of the sheet by some project managers.
Unless I a missing something, a Summary Report won't allow the columns we need and a Row Report doesn't indent or allow me to select high level project milestones.