Count # of networkdays if a condition is not met
Hello,
I want a formula to count the number of workdays between when an item was assigned only if a condition is not met.
=IF(Request Status - Contracting]@row <> "Contract work Complete", [Date Assigned to CM]@row, TODAY())
I want the # of days counted since an item was assigned to a manager only if the manager has not marked the line "Contract work Complete". To make things just a bit harder, I don't want the column "Request Status - Contracting" to equal "Contract work complete" or "Contract work executed"
Thank you for any help! :-)
Best Answer
-
=IF(OR(Request Status - Contracting]@row <> "Contract work Complete",[Request Status - Contracting]@row <> "Contract work Executed"), NETWORKDAYS([Date Assigned to CM]@row, TODAY()))
Answers
-
=IF(OR(Request Status - Contracting]@row <> "Contract work Complete",[Request Status - Contracting]@row <> "Contract work Executed"), NETWORKDAYS([Date Assigned to CM]@row, TODAY()))
-
thank you so much!!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!